Register

Stay up to date with the latest construction and project updates for Olive St Subiaco.

Project Construction Updates

April 2024

Ground floor slab formwork and reinforcement

Significant progress has been made on-site with various works now 100% complete across basement 1 and basement 2.

Additionally, several works are underway, including:

  • Basement 1 to GF AFS walls (75% Complete)
  • Ground floor slab formwork (90% Complete)
  • Ground floor slab reinforcement (50% Complete)

These works form the very foundation of what’ll soon be the Olive St. development. Stay tuned for more exciting updates coming soon!

March 2024

Basement Floor Slab, Footings and Columns

March saw significant progress made with the basement 2 footings, columns, and floor slabs 75% completed.

Shotcrete, the spray method of applying concrete was 90% completed and the inground hydraulic services and stormwater cells were 100% completed as well.

The construction team is on track and every little accomplishment brings us one step closer to completion.

Keep an eye on this page for more exciting updates as the Olive St. development grows!

February 2024

Shotcrete and Basement Walls

Since the new year, piling installation, piling capping beams and basement excavation have been 100% completed.

Additionally, works on shotcrete are 80% complete and the basement 2 blade walls are 70% complete.

It has been a busy start to 2024, but these works are all incredibly important in creating the foundation of Olive St.

Stay tuned for more exciting updates coming soon!

December 2023

Piling Installation and Capping Beams

Last month, the first phase of sewer diversion work was completed.

As a result, works on piling installation and piling capping beams were able to progress.

Both piling installation and piling capping beams are now 80% complete.

From all of us here at Olive St, we wish you a very Merry Christmas and a Happy New Year!

Stay tuned for more exciting updates in 2024!

September 2023

Sewer Diversion Progress

In September, the Olive St construction team completed the first stage of sewer diversion work.

Piling installation is 70% complete and the piling capping beams are 50% complete.

The remainder is set to be installed after sewer works are completed.

Watch this space for more exciting updates as they are announced over the coming months!

August 2023

Demolition Completed

The beginning of August saw demolition completion and the commencement of sewer diversion work.

Piling is currently 70% complete and the remainder is set to be installed after the sewer works are completed.

Construction completion is currently estimated for early 2025.

Stay tuned for more exciting updates!

May 2023

Construction Underway

Construction is now officially underway at the Olive St. apartments with earthworks and piling now in progress on site.

Stay tuned for future updates & see this amazing apartment community starts to take shape over the coming months.

Residential Enquiries

Jones Realty & Projects

Steve Jones 0435 407 837
enquiries@jonesrealty.com.au

Pointe Property

Joyce Li 0452 518 605
joyce@pointeproperty.com.au

Retail, F&B, Office Sales & Leasing Enquiries

Realmark

Brent Griffiths 0402 609 126
bgriffiths@realmark.com.au

Display Suite
53 Rokeby Road, Subiaco

Open
8.30am – 5pm, 7 days a week
or by private appointment

Request a viewing